Factored estimate

Last reviewed:
An early estimating method for process plants in which total installed cost is derived by multiplying the cost of major equipment by empirically established factors.

In process industries, the cost of the major equipment is knowable early — vendors will quote a compressor or a column from a datasheet long before the plant is designed. Factored estimating exploits the observed regularity that everything around the equipment (piping, steel, instruments, electrical, civil, installation labour, engineering) bears a fairly stable ratio to the equipment cost for a given type of plant. Multiply the equipment total by an overall factor — the classic Lang factors run roughly from three for solids-handling plants to nearly five for fluid-processing plants — or apply component factors per discipline for a finer result, and a total installed cost appears from remarkably little definition.

It is the workhorse of order-of-magnitude and study estimates, and it fails in predictable ways: factors calibrated on greenfield plants applied to revamps inside a live facility, unusual metallurgy that distorts the equipment-to-bulks ratio, or site conditions the reference data set never contained. A factored estimate is an analogy, and it is only as good as the resemblance.

See this workflow in practice.

Book a demo to see how Armeta applies this concept across the drawings, standards, specifications, and project data that define the work.