What is Front-End Engineering Design (FEED)?
Where FEED sits in the project lifecycle
A typical major capital project progresses through:
- Concept / FEL-1 — high-level feasibility, order-of-magnitude cost estimate (typically ±50 percent)
- Pre-FEED / FEL-2 — refined process selection, preliminary cost estimate (typically ±30 percent)
- FEED / FEL-3 — defined engineering package, bid-quality cost estimate (typically ±10 to 15 percent)
- Detailed engineering — full design package, construction documents
- Procurement and construction
- Commissioning and startup
The FEED phase is the bridge between a concept the business has decided to pursue and a project that can be executed by an EPC contractor. It is also the phase where most of the engineering decisions that determine project cost and operability are locked in.
FEED deliverables
A typical FEED package includes:
- Process Flow Diagrams (PFDs) and heat and material balances
- Piping and Instrumentation Diagrams (P&IDs) — typically at approximately 80 percent completeness
- Equipment data sheets for major equipment
- Plot plan and equipment layout
- Preliminary piping and electrical specifications
- Initial control system architecture
- Hazard identification study (HAZID) and preliminary HAZOP
- Cost estimate (typically ±10 to 15 percent accuracy)
- Preliminary project schedule
- Constructability review
Duration and cost
FEED duration depends on project complexity. A major grassroots refinery or petrochemical facility might require a twelve-to-eighteen-month FEED with dozens of engineers across multiple disciplines. A unit-scale project might run six to nine months with a smaller team.
FEED cost typically runs 2 to 5 percent of total installed project cost — substantial in absolute terms but leveraged against the project decisions it enables. A well-executed FEED reduces execution cost risk; a poorly executed FEED is where most megaproject cost overruns are seeded.
The role of P&IDs in FEED
FEED P&IDs are not the same as operations-ready P&IDs. At the end of FEED, the drawings are typically at approximately 80 percent completeness — the major equipment, lines, and control strategy are defined, but the full instrumentation detail, relief system design, and tie-in details are finalized during detailed engineering.
FEED-stage P&IDs are used for:
- Preliminary HAZOP analysis
- MTO for bid-quality cost estimation
- Plot plan and piping studies
- Equipment sizing and specification
- Control philosophy development
The transition from FEED to detailed engineering is a drawing-intensive handover. Engineering firms and EPC contractors commonly inherit FEED drawings from a different contractor than the one executing detailed engineering — creating the same drawing interpretation challenge that operators face on brownfield revamps.
Start with ten of your own drawings.
Definitions are context. The fastest way to see what Armeta does for the workflow this term sits inside is to run it on your actual P&IDs.